Milestones and Dependencies

"Milestones are tasks which have no duration but which have a scheduled due date."

But they do have a duration. 

If I have tasks that have a dependency on an external event that is marked as a milestone (e.g. cannot start until the milestone has passed and must start as soon as the milestone has passed), Wrike treats the milestone as having a duration of 8 hours and the tasks are pushed to the next day on the Gantt chart.

How can I get around that?

I have resorted to using timed tasks with a very short duration (15m) but that's not really an accurate representation of what's happening. The external event isn't a task for us, it's a gate and trigger for work.

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
4 comments

Hi Glen, thanks for posting 🙂 I think that Lead time functionality can help you here. You can create a Finish to Start dependency between your milestone and the next task in the chain so that it starts at the same date as the milestone task, please see the screenshot:

Please let me know if that's what you were looking for 👍

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Thanks. This is what I was looking for, but I'm not sure I've fully wrapped my head around it yet.

I think I understand lag time.

  • If 2/Task B starts 7 days after 1/Task A finishes, the predecessor on 2/Task B would be 1FS+7d.

I'm having a harder time wrapping my head around lead time.

  • If 2/Task B finishes 7 days before 1/Task A starts, the predecessor on 2/Task B would be 1SF-7d.

Is that right?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Glen, your lag time example is correct, as for the lead time example, lead time designates that the next task in the chain can start N days before its predecessor has finished, for example: you have your external event as a milestone (a one-day milestone) and it's due 29.03 and a task that should start on the same date, you can set the dependency for the task as Milestone FS - 1d. Hope this helps 🙂

 

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

2
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Thank you.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Milestones and Dependencies
[this list is visible for admins and agents only]

Top

Upcoming Live Sessions

Didn’t find what you were looking for? Write new post