    Glen Turpin commented,

    Liam Darmody, the documentation at https://help.wrike.com/hc/en-us/articles/360013445394-Blueprints is a good summary.  Some of the more interesting ways to use forms and blueprints applies to circ...

  • Avatar

    Glen Turpin commented,

    Liam Darmody I prefer using a form that funnels into a blueprint for several reasons.  Asking questions on the form to capture additional information about the project. Keeping certain fields cons...

  • Avatar

    Glen Turpin commented,

    Same issue here. We're trying out some alternate names for it internally and we're going to change the logo as soon as we settle on one that we like.   I understand how hard it is to brand products...

  • Avatar

    Glen Turpin created a post,

    Best practice for structuring multi-channel marketing projects

    I'm a fairly new Wrike user and I'm trying to come up with the best way to structure some of our project blueprints so that they meet all of our different business needs. I've tried a few different...

  • Avatar

    Glen Turpin commented,

    Thank you.

  • Avatar

    Glen Turpin commented,

    Thanks for that. I'm still having problems, though. I have custom fields with data. I have a calendar that I think is configured correctly. You can't see it in this screen shot, but it's looking in...

  • Avatar

    Glen Turpin commented,

    Thanks. This is what I was looking for, but I'm not sure I've fully wrapped my head around it yet. I think I understand lag time. If 2/Task B starts 7 days after 1/Task A finishes, the predecessor...

  • Avatar

    Glen Turpin commented,

    Thanks for the reply, Lisa. Sorry that I was unclear. I meant something more like this, where custom field becomes one of the possible filters for a calendar.

  • Avatar

    Glen Turpin created a post,

    Calendar from Custom Field

    Can you make a calendar from a Custom Field? I've been poking around and I don't think you can, but I'm hopeful nevertheless.

  • Avatar

    Glen Turpin created a post,

    Milestones and Dependencies

    "Milestones are tasks which have no duration but which have a scheduled due date." But they do have a duration.  If I have tasks that have a dependency on an external event that is marked as a mile...