Lock individual tasks within a project

It would be very helpful to be able to lock certain deadlines of a project.  Some of the tasks have hard deadlines, while others can float.  When you use dependencies and move a not critical task, it moves all the tasks associated with it.  Being able to lock the critical tasks will be VERY HELPFUL!

25
5 comments
Spot On Innovative Approach Stellar Advice
Avatar

changing the critical tasks to 'Milestones' may help.

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

I agree with this. Wrike currently doesn't allow locking of both Tasks and milestones. It would be nice to be able to lock and allowing the manager to be able to move it. Ability to lock the milestone will be a great tool to help tracking the progress and potential delays which may effect other projects and work flow.

1
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Hello,

This is a critical issue for us too.

Is there any plan to address?

Cheers,

JG

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Hi everyone, thanks for your input here 🙂 For now I don't have an update for you. Our Product team estimate the popularity of suggestions here using the number of votes it gets, so it will help if other Community members +1 this feature. 

Lisa Community Team at Wrike Become a Wrike expert with Wrike Discover

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Hi Lisa,

Our Structure in Wrike currently looks like

Main Folder  -> Global Project -> tasks -> subtasks 

                     ->Country Project ->tasks ->subtasks

We would like to make it as (desired)

Main Folder -> Project -> GBL Tasks ->Subtasks

                                     ->Country 1 task -->Subtask

                                     ->country 2 task -->Subtask

In my desired structure, each task belongs to a owner and the set of subtasks belong to different team. Is is possible for everybody to view and comment on all tasks but advanced option like creating dependencies, moving projects, etc is locked. Ie.  GBL Task to GBL team, Country 1 task to Country 1 team and Country 2 task to country 2 team? 

0
Comment actions Permalink

Folllowing List for Post: Lock individual tasks within a project