Planned vs Actual

Hi, There is an issue that I have been facing lately while managing projects that I wanted your team to address:

In a given project, when I set due dates and the task is overdue, it shows that in overdue tasks but as soon as I change the status to complete after the due date has passed, nowhere does it show that the task was completed with delay. The status says completed and the timeline also displays them in green colour. Even when I open the analytics tab to view project report, the report does not tell me that tasks were completed after delay.
I want a clear indication of which of the project tasks were delayed and by what number of days even after they have been completed, how do I achieve this in Wrike?
I also want a comparison of planned duration vs actual duration taken to complete all the tasks. Moreover, I want the timeline to indicate the actual dates that tasks were completed on and not just the dates that they were planned to be completed on.

35
11 comments
Spot On Innovative Approach Stellar Advice
Avatar

I think so too. It's good request.

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar
Stephen

Hi guys, can you vote for this request and feel free to add any use-cases here to help our team better understand the implementation. Thank you!

Also, Vincent shared a workaround he uses for this which might interest you 👍

1
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Hi Guys,

Quick up here.

I went through the other post too, but the other one is mostly about time tracking and budget tracking.

 

Here I join the initial request, about Project Initial Planning VS. Project Executed Planning - Comparing the actul project execution vs. the baseline of the project.

2 examples attached, where you can see with a shading and/or overlay the different between both.

This is really key in addition of the lead and lag management when following project.

 

thansks much

 

Julien

 

 

3
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Hello everybody,

I have the same requirement and I really need this feature. Delays have to appear graphically somewhere. I understand that Wrike is designed to be updated day by day and we do so. But, for instance, if the start date and due date of a task are written in a contractual agreement, I really don't want to modify them in Wrike because also terms in delays are specified in a contract with our customer. So, in this case a Gantt chart with delay bar would come extra helpful. This is what I am expecting.

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Hey guys, thank you for sharing your use-cases here 🙂 Just wanted to mention recently released Baselines in Gantt Chart here. They enable you to compare your project's current schedule to the schedule it had on a particular date in the past. Please check them out and let me know what you think 👍

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Adding on to this conversation, which I understand is a few years old - I, too, would like to see projected vs actual.  My ideal project setup:

Table/List Field Options: 

  • Duration (How long this task is expected to take with the option to NOT change when editing dates.  10 days is 10 days, regardless of start/end/completed dates and adjustments)
  • Start Date (This date should have the option to automatically pre-populate based on dependencies and actual completion dates of predecessors, but still have the flexibility to be manually adjusted)
  • Due Date (Automatically calculated based on SET duration and start date) 
  • Actual Completed Date (Date the task was actually completed, able to manually edit - Option for this date to pre-populate start dates for any successors.) 
  • Actual Duration (start date compared to actual completion date to identify the total number of days it actually took) 

The priority of the requests are as follows: 

  1. Make a way for duration date to be SET.  Not change when we work/update dates. 
  2. Allow dependencies to pre-populate start dates (based on predecessors and then calculate due dates based on the SET duration)
  3. Actual Completion Date that can be better reflected in Gantt Charts and reports to show when tasks are not on target.  
  4. Actual Duration date or formula option to calculate this (Start Date to Actual Completed Date - for the life of me cannot figure this out, if it is currently available)
  5. Able to edit completion dates!  Do not understand the logic of this field being un-editable and only sets to the date marked in Wrike.  

I have been trying to find the best way to replicate the above preferences, and it has not been easy.  I overall made a templated project, and took a screen shot of my set duration expectations.  I then have to constantly update my durations as I work on dates because they change with my date changes (even if I just update start date).  The actual completion date I realize are “custom fields” but they do not reflect as desired in reports and charts.  Any insight that I have overlooked would be helpful.  

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Thank you for your detailed feedback Lisa Thompson

In this thread I showed another Community member how you can track due/completed dates in Wrike reports using calculations. Please check it out - I hope it can be helpful! Completion dates are currently not editable because you can edit the due dates but it's helpful to be able to track and compare due dates with the days when tasks were actually completed. 

I'm passing your feedback on to the Product team now; please let me know if you have any questions - I'll be happy to help.

Welcome to the Community! 🙂

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

1
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

I am amazed this isn't already a feature to view planned vs actual dates in the gantt chart view. 

Are there any updates from the Product Team as to wether this is on the roadmap at all? Would be very disappointing if it's not something you're looking to build, it's such a clear and obvious requirement.

Thanks,

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Welcome to the Community Ash Hallett! Have you tried using Gantt Chart snapshots to compare dates? You can create a snapshot for particular dates and compare the deliverables using it. 

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Following. If this worked, I might be able to use this for our roadmap too. I wish the gannt chart bar would show original dates in red if it's delayed. My only workaround is to update the due dates, leave the start date, and display a custom notes column to show Due: MMDDYYYY

 

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Hi Jeanne Gonzalves! Have you tried using Gantt Chart snapshots to compare your projects' states at different periods of time? Also, it's possible to highlight overdue tasks on the chart:

Please let me know if that could help! 

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
Comment actions Permalink

Folllowing List for Post: Planned vs Actual
[this list is visible for admins and agents only]

Top
Didn’t find what you were looking for? Write new post