8hr/day to 24hr/day Calendar option

We are a 24-hr / 7 day a week organization and scheduling projects is a problem in Wrike when scheduling tasks that are longer then 8hr.  Everything over 8hr's defaults to 1day in Wrike.  I need the ability to schedule tasks that are longer in cases where shifts are 10-12 hours or when is a task will take 40hrs but can be handed off to multiple shifts and get complete in under 2days opposed to 5days.  Please advise if there is a plan for this type of upgrade or work-around.

Upvote 1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
8 comments

Hi Mike Verbeek, can you explain better?
You can create activities longer than 8hr and you can expand Daily capacity till 24h.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hello - Yes. For example, I have tasks that are 19hr of effort and I would like the duration to match.  When I add 19hr in the duration column it automatically changes to 2 days 3 hours.  We have tried to change the work schedule for certain resources from the 8hr/day to 24hr/day like you mention, but it has no impact to the schedule.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Mike Verbeek, you need to use Effort.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Not sure I understand.  Can I do effort-based schedule?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

HI Mike Verbeek

First of all I suggest you to read these articles about Effort:
https://help.wrike.com/hc/en-us/articles/360010852973-Task-Effort-in-Wrike
https://help.wrike.com/hc/en-us/articles/1500005128281-Enabling-and-Editing-Task-Effort-on-Workload-Charts

 

In each task you have 2 different informations:
- Duration (how many days are from start to due date) for example: 1d, 2d, 3d etc
- Effort (how many hours and minutes you want to plan to work) for example; 2h or 1h45m

The Duration specify when you have to do the activity, the Effort specify how much time you want to spend.

So you can have a task that has start date as today and due date as tomorrow (and you wil see 2days of duration) and has 12h of effort.

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Thanks.  I understand that.  I want a task that has 15hr of effort and 15hr of duration, so it starts at 8:00am and finishes the same day at 11:00pm. Or 4hrs of effort = 4hrs duration, not 1/2 day.  Can that be done?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Mike, I don't know if it's yet available.
Lisa  @... I found this page https://www.wrike.com/blog/set-hours-in-task-duration/ but I don't know if it's possibile.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Juan

Hi Pietro Poli, thank you for all your help here!

Mike Verbeek, although it is not possible to define the time when a task should start and end (for example: start at 9.00 AM and finish at  6.00 PM), you can indeed change the daily capacity of the relevant users so that a task which requires, for example, 18h of effort would be completed in 18h, and not in 2.25 days (as it would be if the default 8h daily capacity was in place).

I hope this information helps!

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: 8hr/day to 24hr/day Calendar option
[this list is visible for admins and agents only]

Top

Upcoming Live Sessions

Didn’t find what you were looking for? Write new post