Create report not started tasks after start date
Title pretty well sums it up. Can I create a report to show which tasks show not started after start date. Even better would be if I could combine to a list of task that are not started or delayed (custom workflow) past start date. Any help appreciated.
Hi John Steigerwald,
you cannot achieve this in a single report.
Dates conflit.
You can create a dashboard with two different widgets.
One for Task not started after start date and one of task not started or delayed with past start date.
1. Create an automation rule that would move/include these tasks to a folder if they have a specific status (e.g. "Not started") and their start date has passed: