[Status: Launched ๐Ÿš€] Leads and Lags with Dependencies

How does one add a lead or a lag to a dependency.

For instance, I have a SS dependency between taskย 1 (painting the cabinets) and taskย 2 (sealing the cabinets).ย  Taskย 2 can start when taskย 1 starts, but two hours must elapse from the time the first cabinet is painted until the sealer can be applied (I have two people working, so it's not necessary to complete the painting of the cabinets before the sealer can start going on the ones that are dry).

Soย for taskย 2 itย would look something like this for the dependency: 1SS+2h

How is this done in Wrike??

Upvote 164
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
150 comments
Avatar
Anastasia

Hi Megan! Since scheduling is currently based on dates (and not time) in Wrike, this can be done with the help of Date Constraints. They indicate the earliest date a task can start, and after one is added, the task can't be rescheduled to a prior date. To add a constraint, switch to the Timeline View andย reschedule the dependent task by dragging and dropping it to a different start date. Hope this helps!

-3
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
ย 

Miriam Ivenshitz

Jan 16, 11:07 PM PST

I agree with Megan that this is one of the main things missing in Wrike. I understand that a constraint may be added to a start date, but then this option will not allow automatic date adjustment when the predecessor date changes.

20
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Thanks for your comment Miriam. ย Was trying to work through what was suggested above with the constraints and had the same problem - once the predecessor is updated, the date constraint may become inaccurate. ย Really hope that the Wrike team considers this. ย As well as subtask dates driving the parent task dates. ย That is a HUGE deal to many here on the community to be able to better use Wrike. ย You can vote on my post for this idea here:ย https://help.wrike.com/hc/en-us/community/posts/115000153945-Allow-Subtasks-to-Update-Start-and-End-Dates-of-Parent-Tasksย ย 

ย 

16
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
Avatar
Anastasia

@Miriam, thank you forย sharing your insight, this is really helpful.

@Megan, I appreciate that you created a new topic for this, thank you for posting the link here!

0
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

@Anastasia, do you think this will be implemented any time soon?

3
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
Avatar
Anastasia

@Miriam, this isnโ€™t on our roadmap at the moment, but our Product Team looks at user feedback to learn about the functionality which is important to you, so itโ€™s great to hear about this from you and Megan (and others).

-6
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Lag option isย really a missing feature in Wrike. I have just tried to add 3 days between two tasks but when I did that, Wrike understood thatย as a constraint (Wrike understood that the second task MUST start on the date I set).

If I understood well, for Wrike, if two tasks has a FS (finish to start) relation, the second task should start immediately when the first task finish (??). No option to add a gap between them?

The first two recommendation when someone learnย MS Project is:

1)ย Set the start date and see the project finish date automatically according to the length and dependency of tasks

2)ย Avoidย constraints (or better saying,ย use constraintsย if really necessary) because constraints could undermine recommendation #1

I noticed that Wrike moves tasks even with a constraint but itย draw a vertical line indicating that there is a constraint. Is there anย update about this missing feature?

18
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
Avatar
Anastasia

Thank you for commenting here and providing these details! While we aren't working on this yet, I think those suggestions are great, and since this request is popular I'm going to go ahead and move it to our new Product Feedback section. Other Community members will be able to add their votes there, as well as continue this discussion. This will be extremely useful for our Product Team. Thank you again for taking the time to share your thoughts about this functionality!

4
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Agree with M. Kuramoto that this is a huge missing functionality. ย Our schedules have multiple instances when leads/lagsย are necessary and the schedules move quite frequently. ย Having the awareness of all manually scheduled lead/lags is not possible. ย 

6
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
Avatar
Anastasia

Hi Brad, thanks for commenting here and sharing your insight!

0
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Not being able to enter leads/lags is a huge disadvantage of Wrike. Leads/lags are required to be an all in PM solution. I hope this will be implemented soon.

14
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Plus one for lead and lags. I am just evaluating Wrike for my team, and this is a real negative point...ย 

10
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

No lag option, please add this functionality!

As a quick-win you can add another task called "Lag for certain task" and connect it between the tasks that you need to separate with a lag.

Or for Megan process this task will have a name "Drying lag" or "Cementing lag"

7
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Agreed! This has been one of our biggest issues onboarding Wrike in our organization. In training we were told every extra click costs the user 3 seconds. Without the lag functionality on projects with many steps that are 6-7 months long across a 200 person team, you can imagine how much lost productivity we experience manually fixing these dates.

6
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

I'm experiencing this now as I set up our templates. We may have several month gaps in between tasks being done, and some tasks NEED dependencies but don't necessarily have a due date. This is definitely a HUGE disadvantage as when I'm putting in my dependencies, I must drag the task back to the original date I had set instead of the day after the first task is completed.

6
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

We are also very interested in this functionality (adding a lead or lag time between dependent tasks).ย  The workaround of adding a lag task is quite cumbersome.ย  Thank you.

9
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

The absence of lead and lags is pretty much a basic functionality of a PM tool. I can not understand why this is not on the product road map. All my projects have a requirement for this. So while I really like Wrike I am not sure I can use it effectively to manage my projects. I will have another review and see if I can come up with a work around but if I can't I will need to move to another solution.

9
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Thank you for this thread. ย We have been evaluating Wrike for ourย company's enterprise PM system. ย The lack of easy lag dependency linking is a show stopper and I will now move on to evaluate other PM systems... unless Wrike will be rolling out a new version in the next 30 days that has this feature. ย 

6
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

+1 for adding Leads and Lags. I was very surprised that this feature was not already in here as it is a very critical part of any project. While we can add task "placeholders" for the time being, that is very cumbersome and as someone mentioned, time consuming to add in every single spot that you need a lead/lag. This is a very simple thing to code, please add this feature asap.

10
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

I need this as well.ย 

5
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Missing Lead/Lag and auto adjust of parent task duration will likely be a non-starter for us to use this tool moving forward.

6
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
Avatar
Stephen

Hi all, thanks for your continued votes and input here. If and when I have any updates to this, we'll be sure to post here. Thanks ๐Ÿ‘

1
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Me too me too. Luckily my project with lags can support adding "lag tasks" this time.ย  Please - lead/lag times!

5
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Leads and lags are CRITICAL in project planning!ย  Thisย would be a deal breaker for my organization in using Wrike.

8
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

One more vote. Frankly after reading through all the previous votes I'm falling out of the honeymoon phase. I think the Product Team from Wrike needs to comment immediately that this is on the roadmap and is the process of being scheduled.ย 

Any project planning tool worth its weight would have Leads and Lags and wouldn't be forcing users to create dummy tasks between real work items.ย 

This is on you, Wrike.ย 

6
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
Avatar
Stephanie Westbrook

Hi everyone, we recently released the new Timeline, and the team has included lead and lag times as improvements that they want to make to the view. We still don't have dates to share, but Iย wanted to let you know that it is something that they are planning. You can see more planned next steps for the Timeline View on our Changing to the New Timeline page.ย 

2
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

WOOT! Way to go! ๐Ÿ™Œ

2
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

Any updates on this feature? Excited to add this finally to our very large multi-step projects.

2
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos
Avatar
Stephen

Hey Jennifer,ย this is something our Product Team is looking into at the moment. I have no concrete dates to share, but make sure to click 'follow' on this threadย and I'll provide updates as I have them ๐Ÿ™‚

4
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos

I know this is in the works, but wanted to add in my vote.

We are a machine build shop and this functionality is very important to us.ย 

Myย real world example:

Machine Buildย can start onceย SOME parts are machined, do not have to wait forย ALLย parts to be machined.ย  Same with wiring panels, programming etc.ย  Many tasks rely on each other but do not necessarily have to be complete for the next to start.

Adding tasks just to build in this lag is cumbersome and a waste of time.

ย 

7
๐Ÿ‘ Spot On ๐Ÿ’ก Innovative Approach ๐Ÿ’ช Stellar Advice โœ… Solved ๐Ÿช„ Remove Kudos