TL;DR

Item view opens as an overlay when you click a task from any view (Table, Gantt, etc.). Use it to manage task details - rename, set status, assign people, edit dates, add files, comments, dependencies, and more. The three-dot menu offers extra options like full-screen, starring, recurring tasks, sharing, printing, and deleting.

Table 3. Availability - Legacy plans

Availability: Legacy Free, Legacy Professional, Legacy Business, Legacy Enterprise; Unavailability: ;

Table 4. Availability

Availability: Free, Team, Business, Pinnacle, Apex. ; Unavailability: ;

Overview

Use Item view to see task details. When you click a task from any view, the Item view opens as an overlay.

From Table view

Table_view_overlay.gif

From Gantt chart view

Gantt_chart_overlay.gif

How to Navigate Item view

You can do the following from Item view:

  • Rename a task 1.
  • Tag a task in additional locations 2.
  • Change the Status of a task 3.
  • Add, remove or view Assignees 4.
  • Change or edit scheduled Dates 5.
  • Change a task’s Importance 6.
  • View the Author name 7.
  • View Created date 8.
  • View Task ID 9.
  • Access a task’s Permalink 10.
  • Attach files directly to task 11.
  • Create Approvals 12.
  • Create Dependencies 13.
  • Add information to the task’s description field 14.
  • Add a comment directly to the task 15.
Item_view.png

By using the three-dot menu in the top-right corner of the item view, you can:

  • Expand the item view to full screen or open it in new tab 1.
  • Star a task 2.
  • Add a task to My to-do folder 3.
  • Add a task to the Calendar 4.
  • Duplicate and save a task as a blueprint 5.
  • Make a task recurrent 6.
  • Share and edit with whom the folder is shared with 7.
  • Follow and edit who follows the respective task 8.
  • Print the item view and update through email 9.
  • Delete the task 10.
  • Change the task’s item type 11.
  • Convert a task to Milestone 12.
Three_dot_menu.png

Note

More fields section is not supported in custom item types on mobile apps.

 

FAQ

Can the custom fields order be changed in the 'More fields' section?

Fields inherited from parent locations are sorted alphanumerically in the More field section. If you wish to put fields into a particular order, you can create a custom item type and adjust its settings.

Was this article helpful?