Tasks NOT obeying or following predecessor relationships constraints in Gantt chart

I spent 3 1/2 hours searching for answers and trying to figure this out.  Now that I have a simple answer, I wanted to share it.  Anna in Wrike Support helped me solve it.

If your tasks are not following the predecessor dependencies, then do the following.

Check for "Start Constraints" on your tasks, or add, remove, and edit date constraints on the table portion of the Gantt Chart.

  1. Select a folder or a project from the left-hand navigation panel.
  2. Switch to the Gantt Chart.
  3. Click the gear icon at the top left of the table portion of Gantt Chart, right above the task numbers.
  4. Check the “Start Constraint” checkbox in the pop-up that appears.
  5. Click anywhere outside the window to see the new Start Constraint column in the table.
  6. Find the needed task and CLEAR the date constraint in the “Start Constraint” column so that it will obey the predecessor.

Your tasks will once again follow their predecessors and behave as you would expect them to.

What causes these constraints to get entered when you didn't do it?  It can happen sometimes when changing duration of tasks that are in a linked dependency chain (what happened to me), or it will happen when you manually drag task bars on the Gantt chart view.

I hope this helps someone.

4
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
4件のコメント

I have been running into this issue but it does not work for me. Can someone help?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Komal Thukral 👋 Our Support agent has reached out to you about this via email - if you are still experiencing this, please reply to my colleague 🙂

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi I'm also having this issue, I'm guessing there is a bug where updating the dates of a project while in Gantt view overrides the auto-updates of dates even when predecessors are correctly assigned and there are no start constraints. Can someone help me with this?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Kiran Sohanpal, welcome to the forums 👋

I can see you've discussed this with our Support team already 👍 Let me know if there's anything else we can help you with! 

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Tasks NOT obeying or following predecessor relationships constraints in Gantt chart
[this list is visible for admins and agents only]

トップ
Didn’t find what you were looking for? Write new post