Importing Task dependencies

I have been trying to incorporate dependencies into imported plans for a few weeks now. Plans that have been exported into Excel have a column named 'Depends On' holding the dependencies. However when I Import the file Wrike reports a Server Side error. After some trial and error I found that it was this column that was causing the error. If I leave it out the file loads, but I have no dependencies. I've tried renaming the column to 'Predecessors' which is the name given in the various plan views, but although the plan will import Wrike ignores the column. I assume that it is ignored because the column title is incorrect. Does anyone know if it is possible to include dependencies in an Import?

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
7件のコメント

I encountered the same issue. I tried several variations to import the dependencies according to the Excel import instructions, but without success. I have opened a support ticket and am waiting for a response. I will update if a solution is found.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi folks! I've just looked at our documentation on this, and it looks like the column should be called "Depends On" and then you need to input dependencies in a specific format e.g. "2SS" (start to start dependency on a task in row 2). But there may be some issue so Shay Ron thanks a lot for reaching out and please do let us know after you talk with our Support agents 🙌

Lisa Community Team at Wrike Wrike Product Manager Wrike DiscoverでWrikeの専門家になりましょう

Lisa Wrike Team member Wrike DiscoverでWrikeの専門家になりましょう

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

this isssue is happening again. I imported a couple of weeks ago, and it worked correctly, but now it is again ignoring the predecessors in the column named Depends on

 

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Astrid C, thanks for reaching out. I can see that you are in touch with our Support Team. I hope they were able resolve the issue. Please let me know if you require any further assistance 👍

Rohan V Community Team at Wrike Wrike Product Manager Wrike Discover で Wrike のエキスパートになろう

Rohan V Wrike Team member Wrike Discover で Wrike のエキスパートになろう

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Have the same problem in July 2025. Predecessors listed in column "Depends On" of import file, but not imported to Wirke. Please provide solution.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Maciej Cyprowski

Do have a start date and end date for your tasks? That was the issue in my case, I didnot have any date for any task. The solution was to define the schedule at the beginning of the dependency chain, I added start and end date only to the first task and got the dependencies of all tasks imported.  

 

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Yup, that was it. Adding start date and end date helped. Thanks a lot.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Importing Task dependencies
[this list is visible for admins and agents only]