Show Status change date

Hi,

I`m looking for a way to have a report which shows the duration (days) that a task sits under a status.

For example: 

I have a workflow of 4 stages - (1.Design, 2. Build, 3. Implementation, 4.Completed)

A task was created straight to "Design" and across 30 Days moved through all statues to "complete".

I need a report showing:

Design - 10 Days

Build - 10 Days

Implementation - 9 Days 

Complete - 1 Days

 

Any options to do this?

 

 

8
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
8 comments
Avatar
Hugh

Hi Ben Levitan, welcome to the Community!

It's possible to see this information through a Workflow Report. This will provide you with the information you need!

You can enable Workflow Reports through our Labs feature. Be sure to check out some of the other features there 😊

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Huge,

Thanks for the feedback. I`ve tried using Workflow report, unfortunately, this does not meet my needs.

I`m looking for a report that can provide me this input on a task level, not as an average but rather on each every task.

I`m using Wrike in this case as a ticketing system. each task is a tickets which moves between statuses. looking to find a way to identify time spent in each status.

 

 

3
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Hugh

Hey Ben,

It is currently not possible to generate a report that provides the information that you are describing in your comment.

I'd recommend adding your upvote and comment to this post. Once that post reaches 60 upvotes, our Product team will be able to provide you with a status update letting you know about the possibility of this feature being added to Wrike!

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Ben Levitan I wanted to do something similar too, but found it isn't possible. I was hopeful that with Automations that there would be some hack, but no luck. So, here's what I did: it's not automated, but does allow me to show the info I wanted to display on a dashboard. I just created a custom field that I titled 'Date Status Changed' and then make sure to update that when I change the project status. I display this custom field on the dashboard.  Hopefully they will add the functionality to Automations to insert a date into a custom field upon a status change.

2
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Cansu

Welcome to the Community and thank you for sharing your tip Marcus Rosenthal🙌🏼

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Marcus Rosenthal
Just wondering if you have achieved your status change report via CF automations rolled out this year?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

The below post has 87 likes related to an automation action enhancement that would solve our use case need for reporting on status durations so am hopeful it will be considered. 

https://help.wrike.com/hc/en-us/community/posts/21469783030167-Automation-Action-Change-Custom-Field-Dates

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Thanks a lot for posting the link here Ross Wilson! As mentioned in that thread, that's something our team would like to do. We'll keep you updated 👍

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos