Updated workload during the day
Hi, we use the workload overview on a daily basis to allocate our resources correctly. To make our work easier it would be great if we could somehow have an overview over the tasks we have not done yet, just as in the workload.
For example: If we have work for 8 hours on a certain day it shows 8 hours in the workload overview. If now I have completed a 2 hour task on that day, i want to have an overview which shows me that I have 6 hours of work left for the day.
Does somebody have an idea how we can set up such an overview?
Thanks in advance :)
Hey Marina, happy to see you on the Community 🙂
The closest thing to what you're asking for is Timesheets - they provide a quick overview of tasks you worked on during a week and time you spent working on them. Please check them out and let me know what you think 🙌
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover
Thanks Lisa!
I will test this and share it with my team!