What is best practice to set up a task duration without "time effort" installed (Business License)

3 comments

  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Trevor Tollefsbol

    Hi Susanne, there is a post in product feedback addressing the need for Lead and Lag time to address this very issue.  Please thumbs-up the original post and provide your request for this.  For now, we're using "soft" time to estimate the total duration a task might take which obviously comes with the same issue you mentioned about over-allocating workload.  This is primarily because we don't have a dedicated project manager to track every individual's workload. 

    As for my preference, I would rather see a realistic picture of the total project timeline than trying to be accurate on a granular level.  The end goal is what really drives the business.  As long as the tasks are showing up in the appropriate team member's to-do list, then the total predicted time shouldn't be an issue.  If users are tracking time, you can always report out how much time was spent on each project for estimating future projects.  Again, this is just my personal preference and may not satisfy your company's needs.

    Cheers!

    Is this helpful? 3
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Michael Michalak

    I would second Trevor's recommendation on voting for the fix... 

    We use a combination of Wrike Milestones, Tasks, and dependencies. Basically you have the start of the milestone out 2 weeks, and it dependent on the 30 minute task. This way you can continue to move the task on your timeline, and still maintain the delivery view with tools like conflicts monitors

    Hope that helps..

    Is this helpful? 1
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Susanne Nichols

    Thanks so much for your answers. I've got the challenge to show our management pretty accurately how much time projects take, and where we have time to add more work to the team members. So over-allocating work isn't ideal in this particular case. I will have a closer look at how to work with milestones, thanks so much for the answers!!!!!

    Is this helpful? 0
    Comment actions Permalink

Please sign in to leave a comment.

Folllowing List for Post: What is best practice to set up a task duration without "time effort" installed (Business License)
[this list is visible for admins and agents only]

Community

Welcome ๐Ÿ––

Hi there! ๐Ÿ™‚ Want to become a black belt Wrike Ninja? Here's how to earn a Wrike badge

Welcome ๐Ÿ–– Have you checked out this week's Release Notes yet?

Hey! ๐Ÿ‘‹ Curious about something? Visit How To to search and ask the Community for answers.

Welcome! ๐Ÿ‘‹ Figured out a good tip or trick? Share it in Best Practices.

Want to connect your existing software to Wrike? Learn and ask how in the API section.