Changing dates

Hello There,

Under one of the statuses, I created 12 tasks. Each task takes a week starting from 1st july on wards. After creating all tasks and setting the required duration, the start date changed.

 So, is there something in WRIKE would help me to change dates for all tasks by changing the start date only?

Thanks in advance

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 comment
Avatar
Stephen

Hi Mohamed, so sorry for the delay getting back here.

it's hard to understand why the date shifted without being able to see this detail in your account. However, if you have dependencies this may have played a part, or if you scheduled the duration to begin on a non-working day as set-up in your account.

It would be great to hear on the above before we investigate further 👍

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Changing dates
[this list is visible for admins and agents only]

Top

Upcoming Live Sessions

Didn’t find what you were looking for? Write new post