Need more than 8 hours/day in Gantt Chart View
I work in IT infrastructure and a lot of our work is after hours to minimize disruptions.
I need to visualize the project schedule for days longer than 8 hours. For example, 24 hour burn-in time is 1 calendar day, not 3 business days.
Currently, the Gantt Chart view is limited to 8-hour days. Can you add the ability to adjust this?
Here's an example of a schedule over 8 hours long, but should only be 1 day, that currently does not visualize correctly:
Hi Laura,
I fully agree with you!
But to get a really smart solution, the max amount of hours per day should depent on the task assignees. Only if we'd be able to consider both off-days and working hours of each individual assignee, the gant chart could provide realistic results.