Create a Comparison of total effort hours for active project types.
I am looking for a way to create a comparative chart that compares total effort hours for Project Request types in relation to each other. I can easily compare project counts as they relate to each other as a percentage of the whole, but project effort hours need to be considered. A low number percentage project type count could actually be the biggest effort hours needed by the team.
Hi Roy Baker 🙋🏻♀️
Sorry for the delay here. Here's how you can create a comparative chart that shows total effort hours for Project Request types in relation to each other.
- Reporting on: Project
- Metrics: Effort
- Break by: Item type
Hope this helps. Let me know if you have any follow-up questions. Thank you!