Resource management - flexible time

I am hoping that there will be some increased functionality to allow flexible time to be applied much more easily.

Have to move between views to apply dates and then effort is not very user friendly.

The way we manage resourcing for our projects is to add a folder with all of the resources listed as a separate task. We then apply effort based on either a daily % of say 50% across the life of the project or 100% or whatever it is. Often though people dip in and out of projects. So we have many situations where we might have say a Domain Architect with the following:

1/7/2023 - 31/10/2023 - 50%

31/10/2023 - 30/6/2023 - 100%

It is very laborious and prone to error to have to go through week by week and adjust the dates. I feel like there must be a simpler way to do this with a date picker that allows multiple date ranges with different % of time applied

Thanks,

Rhonwyn

Upvote 3
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
3 comments
Avatar
Juan

Hi Rhonwyn Williams, thank you for creating this very interesting suggestion, please rest assured that your feedback has been noted 👍

Let us know if you have any additional questions or if there is anything else we can help you with 🙂

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Rhonwyn Williams did Wrike ever get back to you about this feature? My team also runs into this problem where resources dip in and out of projects during different phases and sometimes will be allocated fully during a time frame and then only partially during a different time frame. I would love a feature that we could set date parameters and then the percentage to which that resource will be working on that project during that time. 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Kellie Graham, thanks a lot for sharing your feature suggestion here 👍

In the meantime, if you’d like to see whether there are any workarounds or solutions for the problem you’re facing, please feel free to contact our Support Team as one of our experts may be able to help you. Alternatively, let me know if you’d like me to raise a support ticket on your behalf, happy to help!

Rohan V Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Rohan V Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Resource management - flexible time
[this list is visible for admins and agents only]