Hi,
I have a resource with a full Wrike license (external) who is unable to set start/ end date for a task! The field is grayed out!. This user is not collaborator, so why can't he set the dates?!!
Rafa "Even perfection has room for improvement"
Are you on an enterprise account? Have you adjusted folder permissions? The person could have "Limited Access" instead of Editor or Full access to that particular task. https://help.wrike.com/hc/en-us/articles/209603589-Folder-and-Project-Permissions
Hi Lauren. You can close this conversation. I've raised it on Live chat and currently in discussions with your colleague Denis on this.
Regards
Ralph
Rafa "Even perfection has room for improvement"
@Ralph, happy to hear the Support Team is looking into this for you and your colleague. It would be great to post back here and share the outcome as it may be helpful to other Community members facing a similiar issue in the future.