Assigned Timeline
Is there away to enter a beginning date and end date for a project into Wrike, that will then auto populate dates to assigned tasks that are found between these two dates?
It looks like we don't have the translated page you're looking for, but we do have other content in English and offer support in English.
What can we help you with?
Learn. Share. Discuss.
Is there away to enter a beginning date and end date for a project into Wrike, that will then auto populate dates to assigned tasks that are found between these two dates?
Folllowing List for Post: Assigned Timeline
[this list is visible for admins and agents only]
Hi David, thanks for reaching out here! Since there's no way for the system to know the required duration and order of tasks in a Project, it isn't possible to autopopulate this information from scratch. However, if you have several repeating or similar Projects, I wanted to suggest setting up a template for them. When setting it up, you'll need to enter start and due dates for the tasks, and these dates can later be used by the system as a reference point when duplicating the template. Folder/Project Duplication allows you to choose how you want the tasks to be rescheduled:
Hope this helps! Happy to answer any other questions. :)