Conflict Monitor on Gantt Chart

Table 43. Availability - Legacy plans


Overview

You can add milestone tasks to the dependency chains. However, they don't shift when the tasks in the dependency chain get rescheduled. Wrike comes with a built-in conflict monitor that tells you if the date shift doesn't work for your original plan (because of milestones).

How it works

A scheduling conflict occurs and the dependency arrow 1 turns red if:

  • The predecessor task in a Finish to Start type of dependency is set to finish later than the milestone date.

  • The successor task in a Start to Finish dependency starts earlier than the milestone date.

  • The parallel task in a Start to Start type of dependency is set to finish later than the milestone date.

ConflictMonitor_Gantt.png

You can reschedule the entire dependency chain, including the milestone task. Learn how to do that here.