Conflict Monitor on Gantt Chart

Table 43. Availability - Legacy plans

Unavailability: Legacy Free; Availability: Legacy Professional, Legacy Business, Legacy Enterprise.


Table 44. Availability

Unavailability: Free; Availability: Professional, Team, Business Plus, Enterprise Standard, Enterprise Pinnacle.


Overview

You can add milestone tasks to the dependency chains. However, they don't shift when the tasks in the dependency chain get rescheduled. Wrike comes with a built-in conflict monitor that tells you if the date shift doesn't work for your original plan (because of milestones).

How it works

A scheduling conflict occurs and the dependency arrow 1 turns red if:

  • The predecessor task in a Finish to Start type of dependency is set to finish later than the milestone date.

  • The successor task in a Start to Finish dependency starts earlier than the milestone date.

  • The parallel task in a Start to Start type of dependency is set to finish later than the milestone date.

ConflictMonitor_Gantt.png

You can reschedule the entire dependency chain, including the milestone task. Learn how to do that here.