Creating Tasks on Calendars
All users, except for collaborators, can create tasks from a calendar grid. If the calendar is shared with the user, their access role may restrict task creation.
Note
You can create new tasks only on classic calendar layers.

-
Navigate to the relevant calendar.
-
Click the date you want to schedule a task for. 1
-
In the window that opens:
-
Enter a task title. 2
-
Select a folder, project, or space to tag the task in, you can select more than one. 3
-
Select the classic calendar layer you want to add the task to. 4
-
-
Click Create. 5
Your task is created, and it will immediately appear in the specified calendar layer. If that layer is hidden, it will be displayed automatically.
On week/month views, your task is created as a 1-day task, scheduled for the date you selected in step 2. On the quarter view, the created task has a 5-day duration and on the year view, the duration is 1 month.