Allocate Effort to Milestone
Is there any way to allocate effort to milestones? Some of our milestones are important client meetings/presentations and I'd like to allocate the number of hours that our team members will to spend on those meetings and presentations.
Hey Mya, thanks for reaching out 🙂 Since milestones are tasks without duration, effort can’t be applied to them. What if you created separate tasks for the meetings and presentations where you can allocate effort? I'll be happy to hear what you think 🙌
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover
I'm in the same boat. Milestones still have effort we need to allocate so we can properly resource and plan for our teams. Is this something that could be added?
Hi Megan Radford, welcome to the Community, and thanks for posting 😊
Please allow me to share a little detail on how we process Product Feedback. We receive many great ideas on Community, and we pass on all feedback to our Product team. If you'd like to find out more, this article explains what happens after we receive Product feedback.