Report or dashboard to illustrate the project plan and when it goes off schedule

Project Time Lines: For each new client project, we create a project plan broken down by phases or sprints.  We include our own department resources' effort and duration with predecessors, and key client milestone meetings or specific due dates of when information like collateral or copy is due. We create this initial schedule, work on it with the client to adjust to add more time for reviews, take into account PTO etc, then have them "sign it" once it is mutually agreed upon. 

Problem: Clients often don't pay attention or follow these timelines and the schedule goes off, resulting in extended durations, resources then being over allocated, loss of project momentum, etc.

Solution: We are looking for some kind of dashboard or report that we can show before each client meeting to illustrate where we are in the project plan timeline, where the project has gone off schedule, and the launch delay impact as a result.  Does an existing report or dashboard in Wrike exist that would show something like this?  Ideally comparing the snapshot of the original plan, then a gauge or something visual showing how far off we are from the original plan?

I appreciate this group's feedback on how others solve for this continuous problem.

Danielle

2
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Комментариев: 3
Avatar
Juan

Hello Danielle Wilson, thank you for sharing your use case with us. May I ask you if Gantt chart snapshots could be useful for you? You could create snapshots to clearly compare different states of your projects and better understand how changes in dates could affect your work.
 
 
Would this be an alternative for you?
 
Thank you!
0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Juan,

We do use snapshots to illustrate the project plan with the clients and have even tried the "download to PDF" and send for their approval and signature (which they tend to ignore after the fact). We're looking for a more high-level visual to say "we started the project with these milestones, we are now 2, 4, 6 weeks off" and the consequence of how it impacts the release dates. I don't think the snapshots would be as effective though since you'd have to bring up 2 gantt charts and show the project plan to compare the difference.  That would be a little clunky for our purposes.  

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Juan

Hi Danielle Wilson, thank you for your reply. I understand your point, in that case, the Productivity Analysis or the Project Status templates of Wrike Analyze could be useful for you. In case you'd like to know more about these options, please let me know 👍
 
Thank you!
0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Report or dashboard to illustrate the project plan and when it goes off schedule
[this list is visible for admins and agents only]

Вверх
Didn’t find what you were looking for? Write new post