Change Project Start
Can the project/folder start date be modified after it has been selected? I need to move the project/folder start date back and I can't find a way to do it.
Кажется, у нас нет переведенной страницы, которую вы ищете, но у нас есть другой контент на английском языке и поддержка на английском языке.
Чем мы можем вам помочь?
Учиться. Делиться. Обсуждать.
Can the project/folder start date be modified after it has been selected? I need to move the project/folder start date back and I can't find a way to do it.
Folllowing List for Post: Change Project Start
[this list is visible for admins and agents only]
Hi Brian, thanks for writing in! To change the Project start date, just modify the dates from the Project information panel, as shown here:
Folder durations and dates are calculated based on the tasks inside them, so in this case you just need to modify the tasks inside those locations. Does this help? Happy to answer any further questions!
How do I avoid needing to update all the tasks and just have it calculated based on a new start date?
With lightspeed, the project information panel has disappeared. How do I now edit the start/finish date?
Hey Carmen Lea, that doesn't sound right! Project panel should still be there. Could you please share a screenshot?
Lisa Community Team at Wrike Wrike Product Manager Станьте экспертом Wrike с Wrike Discover
Lisa Wrike Team member Станьте экспертом Wrike с Wrike Discover