Cancelling Project Doesn't cancel tasks
It seems to me that if a project gets cancelled, all the tasks within that project would also get cancelled. That is not the case. When I cancel a project I have to then go and manually cancel all the tasks within the project. Would be great if the tasks automatically cancelled with the parent project gets cancelled.
Hello Robin Hayes, that's correct. I can recommend using the mass edit option to select all tasks under the project and change the status to "cancelled". I've passed on your feedback to the Product team and I'll let you know here if there are any plans to introduce such functionality 🙋🏻♀️
Cansu Community Team at Wrike Wrike Product Manager Learn about Wrike’s killer features and best practices with our Online Training Webinars
Cansu Wrike Team member Learn about Wrike’s killer features and best practices with our Online Training Webinars
@... Yes, that's what I do. Just have to remember to do it! (not always easy 😀).