make only certain tasks visible in timesheet
Hello Wrike community,
Problem: Too many tasks are shown in the item search in the timesheet.
We are facing the challenge within our company, that we have a wide variety of detailed tasks within a project (that we also would like to plan on a daily level.) However, the time management (i.e. booking hours in timesheet) is happening on a higher level (project phase level, which can take months, or years).
When users are trying to book their hours, they cannot find the correct tasks since it is overloaded with smaller tasks for that project (tasks descriptions within the project start with the same project number).
Currently the users need to book their hours via the project itself (see screenshot below).
In that way it appears on their timesheets, and then they can pin this tasks (it will come back several weeks / months).
This is a time consuming workaround if you have up to 30 tasks in your time sheet. This leads to a lot of frustration among the users since they need to book all their spent time in the timesheets.
Is it possible to make only certain tasks visible in the timesheet?
Are other people facing the same challenge? 
Is there another solution that we can consider?
I cannot imagine that nobody in the Wrike community is facing the same challenge?
Hi Bas Rijks,
I think I didn't understand your need at 100%.
Should you explain the information flow better and show us what happens?
You could also use the dashboard to filter certain types of activities.
Basudha Sakshyarika Community Team at Wrike Wrike Product Manager Wrike Discover で Wrike のエキスパートになろう
Basudha Sakshyarika Wrike Team member Wrike Discover で Wrike のエキスパートになろう
Hello Basudha,
Thanks for your suggestion.
Could you please explain me how we could disable the prefill functionality?
Maybe this could be a work around.
thanks,
Bas
Basudha Sakshyarika Community Team at Wrike Wrike Product Manager Wrike Discover で Wrike のエキスパートになろう
Basudha Sakshyarika Wrike Team member Wrike Discover で Wrike のエキスパートになろう
I also struggle with the overload of too many tasks for time sheets. To make it complete I would appreciate to see the following some day:
Thanks much!
Hi Dr. Josef Hartmann 👋 I’m sorry to hear about the difficulties you’re facing. Thank you so much for taking the time to share your suggestions here. If there are any updates in the future, we’ll be sure to share it. Please keep an eye out for our Weekly Release Notes.
Rohan V Community Team at Wrike Wrike Product Manager Wrike Discover で Wrike のエキスパートになろう
Rohan V Wrike Team member Wrike Discover で Wrike のエキスパートになろう