Rescheduling only certain tasks when creating from blueprint

Hi everyone,

I'm looking to create a blueprint that I can use where only specific tasks are rescheduled and some stay at the same. It's an academic year communications plan, so there are two tasks I'm looking to keep their deadlines in September always, but the following tasks are 7 weeks, 5 weeks, 3 weeks (etc.) before each separate event (project created from blueprint). Any idea how I can do this?

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1件のコメント
Avatar
Juan

Hello Emily Koller-Apelskog, welcome to the Community! It is possible to reschedule your blueprint around a specific task, would this be an option for you?
 
Alternatively, you can create dependencies between your tasks. However, there is no direct option to select only some tasks to be rescheduled when creating items from a blueprint.
 
I hope this information helps. In case you'd like to share more details about your use case, please feel free to do it.
 
Lastly, I'd like to mention that you can check our New to Community forum to discover all the resources you can find in our Community 🙂
0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Rescheduling only certain tasks when creating from blueprint
[this list is visible for admins and agents only]

トップ

今後のライブセッション

お探しのものが見つかりませんか? 新しい投稿を作成する