Multiple predecessors

Hello, 

Is it possible to make a task with multiple predecessors? How to write it? 

For example, Task C can begin while Task A and Task B are Finished? 

Thanks; 
Maxime 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1件のコメント
Avatar
Cansu

Hello Maxime, welcome to the Community 👋🏻
 
You can have multiple predecessors of a task. To do that on the Gantt Chart, double click on the Predecessors column on the table and create the dependency. Alternatively, open the task by clicking on the window icon that appears when you hover over a task. From the pop-up window, you can edit the dependencies.
 
  
Please let me know if this helps 🙋🏻‍♀️