Assigned Timeline
Is there away to enter a beginning date and end date for a project into Wrike, that will then auto populate dates to assigned tasks that are found between these two dates?
どのようなことでお手伝いできますか?
学ぶ。 共有する。 議論する。
Is there away to enter a beginning date and end date for a project into Wrike, that will then auto populate dates to assigned tasks that are found between these two dates?
Folllowing List for Post: Assigned Timeline
[this list is visible for admins and agents only]
Hi David, thanks for reaching out here! Since there's no way for the system to know the required duration and order of tasks in a Project, it isn't possible to autopopulate this information from scratch. However, if you have several repeating or similar Projects, I wanted to suggest setting up a template for them. When setting it up, you'll need to enter start and due dates for the tasks, and these dates can later be used by the system as a reference point when duplicating the template. Folder/Project Duplication allows you to choose how you want the tasks to be rescheduled:
Hope this helps! Happy to answer any other questions. :)