Not all assigned tasks showing under "my work"
There are multiple tasks that have been both shared with me and assigned to me that do not appear under "my work" so I miss them. Why is this happening and how do I fix it?
Additionally, when my coworker pulls a dashboard she isn't seeing all of my assigned tasks either.
Hi Sarah! Welcome and thanks a lot for posting your question to the Community. :)
Serge, How to you unpin in bulk? I had a project with hundreds of tasks where every task was assigned to me (because I was the PM and it was incorrectly assigned). I mass unassigned them but because they are all starred they are still all showing in my work making it almost impossible to see my actual tasks.
Hey Michael. Thank you for bringing your question here!
When you're assigned to some tasks - they instantly get to the My Work section. However, if you don't move them inside the section (as in, drag-and-drop between Today, Next Week, etc.), they will be automatically unpinned from My Work once you're unassigned. If some tasks still appear in your My Work section, it looks like you either manually pinned them or moved them within the section. In this case, you can use mass actions within the My Work to unpin the tasks in bulk: