change dates on sub-tasks that are same within a project but under a different main task

I have same sub-tasks for various tasks within the project but need to have different dates depending on the main task.  When changing the date on my sub-task - it changes the date on all sub-task with the same name

0
3 comentarios
Spot On Innovative Approach Stellar Advice
Avatar

Hi Glenda Brungardt, am I right in understanding that you use the same subtask rather than different subtasks with a similar name? To confirm that, please check the task ID. Is it the same for all the items? 

In this case, I suggest duplicating the subtask so that you can edit the items separately and set different dates for them. Hope it helps!

Lisa K. Community Team at Wrike Wrike Product Manager Infórmate sobre las funciones y prácticas recomendadas de Wrike

Lisa K. Wrike Team member Infórmate sobre las funciones y prácticas recomendadas de Wrike

1
Acciones de comentarios Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Thank you - will take this info and see if it solves my issue

0
Acciones de comentarios Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Please let us know how it goes Glenda Brungardt 🤗

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
Acciones de comentarios Permalink

Folllowing List for Post: change dates on sub-tasks that are same within a project but under a different main task
[this list is visible for admins and agents only]

Arriba
Didn’t find what you were looking for? Write new post