Project progress % based on effort instead of duration

Hello,

Our organization uses the Business plan with the Wrike Resource Add-on.
We have issues with the project progress calculation that does not reflect accurately the work done.

We have about 500 to 1000 tasks in a project and in our customized Workflow, we have several validation tasks with an effort set from 1 to 3 hours.

A project progress percentage would be much more accurate if it was based on effort rather than durations.

This is an example of what I would need to be added:
Project progress

Measure as

  • Completed tasks
  • Duration of completed tasks
  • Effort of completed tasks
  • Task and duration average
  • Tasks and effort average
  • Don't meausure progress

 


Upvote 7
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
5 comments

Interesting idea.  I don't put much stock into the progress bar though... it treats all tasks as equally weighted and some tasks just aren't relevant to determining the "completeness" of a project.  I think it would also be a GOOD feature to include a checkbox in any task that if tracking is enabled... you can designate to include a task in the % calculation or not (i.e. a task becomes "key" to measuring the progress of the project).

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Thank you for these ideas, folks! Our team continues working on the project progress functionality, so your feedback comes at a very good time 🙌

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

I agree with this request — in addition, it would be very useful if the calculation could also include the effort of ongoing (in-progress) tasks, not just completed ones. This would provide a more accurate real-time reflection of project progress.

 

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Hi Gilad Hilerowicz 👋 Thank you for supporting Grégory’s feedback and for sharing your idea as well. We’ll keep you updated if there are any developments on this.

Rohan V Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Rohan V Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

We use Wrike Analyze to show Project Progress based on Effort of the completed tasks (out of the total Effort on a Project) but agree it should be available as an option on the Progress Meter for Projects.

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Project progress % based on effort instead of duration
[this list is visible for admins and agents only]

Top

Upcoming Live Sessions

Didn’t find what you were looking for? Write new post