Implement dependencies between activities and projects or between projects and projects
Good morning,
we wanted to ask if it would be possible to implement dependencies between two projects or between activities and projects that are related to each other.
We know that one possible solution is to set the last activity of project A as the predecessor of the first activity of project B, however it would be useful to set predecessors and successors between projects as well.
Hello Stefano Mattalia, welcome to the Community!
Thank you for posting. At the moment, it is not possible to create a dependency between two projects/folders, and unfortunately, it's not planned for the near future. We have an existing thread in our Product Feedback forum in which you can add your upvote and follow all updates in relation to this request.
Hi Stefano, it doesn't work in the Gantt chart (until you tag the related task in both projects), but you can create dependencies across projects, even across spaces in the task view. Just click this icon and add your task.
If it doesn't show up and you can't find it by name, use the ID / permalink.
Note: Depending on the status of the task creating dependencies may be limited. (E. g. You can't add a predecessor to a task that is marked as "completed".)