Maybe I'm missing something, but is it possible to lock the Baseline on a specific date? Every time I go into Analytics view the Baseline has moved to the present day. Does that mean we have to separately note the date we agreed to baseline and feed that in every time?
Thanks!
Hi Arthur Mathie, I'm afraid it is not possible to set a certain date for the Baseline Chart per folder/project. You will need to amend it each time you open the Analytics view.
You are welcome to elaborate on your use-case and post your suggestion in the Product Feedback section for other Wrikers to be able to vote for the idea. Most popular requests get to our product team and end up being added to the roadmap. Thank you!☺️
Lisa K. Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa K. Wrike Team member Become a Wrike expert with Wrike Discover
So that means the user has to make an external note of when the schedule baseline was agreed to, and re-enter that date every time they want to compare the current schedule to the agreed baseline date. It makes far more sense to lock it on an agreed date.
Thanks
Thank you for creating a separate Product Feedback post for your suggestion Arthur Mathie 🤗
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover