Filter active tasks and also active projects

6 comments

  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Brittany Archuleta

    Hi!

    Just wanted to suggest something to you. I find it easier to create a custom Widget to track all active projects and tasks. You can customize it to show all active tasks, tasks to do, overdue tasks etc.ย 

    Just start at the top of the workspace under "Dashboards" & click "Create New Widget" from there you choose your project & check the "Include tasks from Subfolders" box to show all your tasks. You can then apply the filters you want. Here is a link for more about this. Hope it helpsย ๐Ÿ˜€

    https://help.wrike.com/hc/en-us/articles/115004120265-Dashboard-Widgets

    Is this helpful? 1
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Hugh

    ย 
    Thank you for the post! It currently is not possible to view active tasks within a completed project when the "All active projects" filter is enabled. However, Brittany Archuleta's suggestion is an excellent workaround for this and should provide you with the view you're looking for. Thank you, Brittany!
    ย 
    If you need anything else, be sure to let me know.

    Hugh Community Team at Wrike ๐ŸŒŽDiscover... Wrike Discover and become a Wrike expert. Click here to get started

    Is this helpful? 1
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Diandra Di Dio

    Hi Brittany and Hugh,

    Thank you both for your answers :)

    I tried the dashboard but there are so many tasks in our projects and folders that without the tree structure of the space next to it, it's difficult for me to find my way around. I really like the structure the 'table view' gives me.

    However, I don't want to see active tasks in completed projects, I only think my filter doesn't work correctly. I'm sorry if my questions wasn't clear :)

    In the first screenshot, I applied 2 filters: active projects and active tasks (you don't see this second filter on the screenshot but it's selected). But Wrike only shows me active projects. All tasks beneath the projects you see in screenshot 2 aren't shown.

    In screenshot 2, I removed the filter "active projects" and only kept "active tasks". What I see is all active tasks, including completed projects (with no active tasks inside).

    For what I see, Wrike doesn't apply two filters at the same time because "active projects" and "active tasks" result in my view in only "active projects and no active tasks outside projects".

    Do you think this could be a bug? Other members of my team have the same problem.

    Thank you for helping me! :)

    Is this helpful? 1
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Hugh

    Hey Diandra Di Dio, thank you for providing more clarification here!
    ย 
    When you apply multiple filters in a view in Wrike, all of their conditions have to be met to appear in the view. When you filter to show all active projects, it hides all of the tasks outside of projects in the space, as they do not have an active project attached to them that would meet the conditions of the filter. This is why these tasks have been disappearing for you in Table View.
    ย 
    Hope this answers your question! If you need anything else, let me know.

    Hugh Community Team at Wrike ๐ŸŒŽDiscover... Wrike Discover and become a Wrike expert. Click here to get started

    Is this helpful? 1
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Diandra Di Dio

    Hi Hugh, thank you, I understand better the functionalities of the filters now.

    Do you think this is an issue we could add to the 'Product feedback', to be able to filter on the basis of 2 conditions if the project/task only meets one?

    Thanks for your advice!

    Is this helpful? 0
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Hugh

    ย 
    I think it would be a great idea to move this to Product Feedback! This way, other Community members can provide their suggestions, and the Product team will be use this post in their conversations about the product roadmap. I've moved this to the Product Feedback section for you now.
    ย 
    If I can help you with anything else, be sure to let me know!

    Hugh Community Team at Wrike ๐ŸŒŽDiscover... Wrike Discover and become a Wrike expert. Click here to get started

    Is this helpful? 0
    Comment actions Permalink

Please sign in to leave a comment.

Folllowing List for Post: Filter active tasks and also active projects
[this list is visible for admins and agents only]

Community

Welcome ๐Ÿ––

Hi there! ๐Ÿ™‚ Want to become a black belt Wrike Ninja? Here's how to earn a Wrike badge

Welcome ๐Ÿ–– Have you checked out this week's Release Notes yet?

Hey! ๐Ÿ‘‹ Curious about something? Visit How To to search and ask the Community for answers.

Welcome! ๐Ÿ‘‹ Figured out a good tip or trick? Share it in Best Practices.

Want to connect your existing software to Wrike? Learn and ask how in the API section.