Moved final or Go Live Dates
Hello Everyone,
Is there a way to run a report that would show off all of the original go live dates for projects in your Wrike account?
For example we have several projects within wrike that had a set end date, but our consultants kept pushing them back and we would like to see how far they have came or what was moved.
Thank you and let me know!
Hi Jordan Crisman!
I think that project baselines should be helpful in this case. They allow you to compare a project’s originally planned VS current scheduled start and due dates. Here's more info on them:
https://help.wrike.com/hc/en-us/community/posts/360027305473--From-Wrike-Make-a-beeline-for-Baselines-Now-available-in-Gantt-Charts-Wrike-Labs-
https://help.wrike.com/hc/en-us/articles/210323545#baseline
Please let me know if it's useful and also if you have any questions! 🙌