Wrike Integrate - Example recipe to copy the value from a project-level custom field to all new tasks within that project

1 comment

  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    David Laffitte

    Hi Laura - This is amazing and very helpful. I appreciate your work and documentation of the steps. I was able to get it to work after changing the variable names quickly. Below are my two use cases and associated error on the second one.

    First Use Case: Simple task additionย 
    ย  Test Structure - Space > Folder > Folder > Project (with custom field) > Task
    ย  Status - Success! The custom field was copied as expected. :D

    Second Use Case: Sub-task addition
    ย  Test Structure - Space > Folder > Folder > Project (with custom field) > Task > Sub Taskย 
    ย  Status - Error - 400 Bad Request: {"errorDescription":"Operation is not allowed for logical folder","error":"invalid_request"}

    It seems like the "Wrike - Get folder by id" action can't handle sub-tasks.ย 
    https://docs.workato.com/connectors/wrike/get-folder-by-id-action.html

    Have you encountered this?ย 

    Thanks!


    Is this helpful? 0
    Comment actions Permalink

Please sign in to leave a comment.

Folllowing List for Post: Wrike Integrate - Example recipe to copy the value from a project-level custom field to all new tasks within that project
[this list is visible for admins and agents only]

Community

Welcome ๐Ÿ––

Hi there! ๐Ÿ™‚ Want to become a black belt Wrike Ninja? Here's how to earn a Wrike badge

Welcome ๐Ÿ–– Have you checked out this week's Release Notes yet?

Hey! ๐Ÿ‘‹ Curious about something? Visit How To to search and ask the Community for answers.

Welcome! ๐Ÿ‘‹ Figured out a good tip or trick? Share it in Best Practices.

Want to connect your existing software to Wrike? Learn and ask how in the API section.