Duplicate dependency on recurring task

I have a task that occurs the 1st-14th of every month (Task #1).  Following its completion, there's a 3 day internal review period (Task #2). The internal review currently appears as a subtask, dependent on Task #1. Task#1 is set as reoccurring. I would like Task#2 to appear as reoccurring and dependant on Task #1 monthly. Having trouble. Help!

help.wrike.com/hc/en-us/articles/209603769-Make-a-Task-Recurrent?flash_digest=c1b38d9e187437d94c36c15c96d7f1e3cf10573a

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 comment

Hi Taylor, happy to see you on the Community 🙂

Currently there's no functionality to make subtasks recurrent along with the parent task. Please check out this Product Feedback thread - you can +1 the suggestion and add your use-case there 👍

Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Lisa Wrike Team member Become a Wrike expert with Wrike Discover

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Duplicate dependency on recurring task
[this list is visible for admins and agents only]

Top

Upcoming Live Sessions

Didn’t find what you were looking for? Write new post