Schedule by Project
In the new resource management, Is there a way to set a resource's working schedule (days per week, #hours per day, weekend work) by project rather than set by task?
help.wrike.com/hc/en-us/articles/360010835433-Workload-Charts
It looks like we don't have the translated page you're looking for, but we do have other content in English and offer support in English.
What can we help you with?
Learn. Share. Discuss.
In the new resource management, Is there a way to set a resource's working schedule (days per week, #hours per day, weekend work) by project rather than set by task?
help.wrike.com/hc/en-us/articles/360010835433-Workload-Charts
Folllowing List for Post: Schedule by Project
[this list is visible for admins and agents only]
Lisa Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover
Lisa Wrike Team member Become a Wrike expert with Wrike Discover
I already provided the case, "days per week, #hours per day, weekend work". This can vary by project. We have some projects that allow for working on weekends or have longer work days (10 vs 8) We also have vendors on some projects that have 24/7 production hours. It would be nice if I could set the above mentioned items by project rather than individual task. I don't really care if it is in the resource module or the base software.
Suzanne, thanks for clarification! As I mentioned earlier, for now there's no such option. What do you think about adding this post to the Product Feedback section? It'll be highlighted with our Product Team in that section 👍