When you add a Dependency from a separate Folder/Project, how do you view the full Gantt/Calendar with relevant Tasks?
I can add a Dependency across different folders & projects, but then I can't seem to be able to view the relevant Tasks associated in a Gantt or Calendar view. Of course the goal is to be able to see how shifts in certain projects owned bhelp.wrike.com/hc/en-us/articles/209604229-Dependencies-on-the-Gantt-Chart-y other groups will affect the timeline of my group.help.wrike.com/hc/en-us/articles/209604229-Dependencies-on-the-Gantt-Chart-help.wrike.com/hc/en-us/articles/209604229-Dependencies-on-the-Gantt-Chart-help.wrike.com/hc/en-us/articles/209604229-Dependencies-on-the-Gantt-Chart-help.wrike.com/hc/en-us/articles/209604229-Dependencies-on-the-Gantt-Chart-
Hi Mike, I'm very sorry for the delayed response here. For this you'll need to view multiple Folders in the Gantt view, you do this by selecting the Parent Folder/Project of the different Project and Folders to give you a holistic view.
So once you select the Parent (or root) Folder, you'll see all the Folders and Project that are contained within on the Gantt view, including any dependencies.
Let me know if you have any questions 👍