Tracking Slippage

Hi all

When a due date for a project or task is pushed back is there any way of tracking this? I'd like to be able to track slippage for tasks and projects within my organisation. 

Thanks so much

Shona

 

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
3 comments
Avatar
Stephen

Hi Shona, thanks for posting and welcome to the Community!

Have you used the Analytics yet, specifically the Baseline Chart which compares the completed dates to the dates you've originally scheduled?

Alternatively, you can run a Report when the task is completed if you choose the 'completed date' and 'end date' in your Report filters. You can then see side-by-side if dates match up and which ones ran over.

Let me know if these options help 😊

 

2
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

@Stephen, thank you, that helps me as well. I was wondering what the Baseline Chart was for. 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Stephen

Glad I could help 😊

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Tracking Slippage
[this list is visible for admins and agents only]

Top

Upcoming Live Sessions

Didn’t find what you were looking for? Write new post