[Answered] Dependencies on the Timeline View not accurate
AnsweredHello! I have an issue abou the shifting of the dependency chain. It is important for our team that if we change the date of a task the dependent tasks automatically reschedule. Everywhere there is written that this should work. When I move a task to a further date the other dependent tasks also reschedule but not accurate. Between some tasks stays the right gap of days, between others not. For example before there was a gap of two days between the dependent Task 1 and Task 2, but when I shift the dependency chain there is suddenly a gap of four days.
What could be the reason for that? Can somebody help me please? 🙂
Hi Theresa, welcome to the Community!
Good question. It's a little hard to see what's happening without screenshots etc. but I'm thinking perhaps it's because of your working days. Does the 2-day gap stretch to 4 days because the change now pushes the duration over a weekend or other non-working days?
Let me know if this helps, otherwise, I'll raise a ticket to our Support Team who can help by email 👍
Hi Stephen!
Thank you for your fast answer. This is the clue! I didn't think about it. So the problem is solved :)
Ah, perfect Theresa. Don't be stranger around these parts. If you're looking to connect and learn from peers you can always introduce yourself to the Community 😎