Manual Task Progress override
Hi. Im wondering if any knows if its possible to be able to show manual progress of a task/project ratehr than Wrike AI calculates the percentage progress through Completed tasks etc?
The ability is so we can drive the progress manually based on a single task and not driven by the AI. I know w can create a custom field and then have that as a manual % but that means a seperate column and wondered if i could override manually the progress column. thanks
You can't trick the system default column for Progress or override it. But, you can use the custom field, as you mentioned, and then hide the system field so that you don't have duplicate columns.
I have a similar situation; I want to manually calculate project progress as the AI is not doing a good job at it. The AI is showing that all our projects are at risk, and that is so wrong. On the screenshot below, it shows that the due date of this project is not up until April next year, all tasks have been completed on time and as for now there are no delays. We can't use this color code for our upper management because is just simply wrong.
Any way to calculate the progress manually?