Indent Subtasks in Reports

It would be great to have the ability to show subtasks indented under their parent task.

Upvote 2
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 comment
Hi Joe Faulk! Happy to see you here in the community! 🎉
 
It is indeed possible to indent or organize subtasks under parent tasks in Reports. Just click on the view icon in the top left corner when it shows the 'Structured Hierarchical View.' 👇🏼
Hope this helps. Let me know if you have any additional questions. Thank you! 😊