getting dependency arrows in timeline view to work

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
4 comments

I  can't seem to get the dependency arrows to work. Any hints?

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Anastasia

Hi Krista! To add a dependency on the Timeline, hover your cursor over the left or right side of a task bar, and then click and drag the outer arrow to another task. Here's what the process looks like:



Does this help? Happy to answer any other questions! :)

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Thanks. Discovered that I had the status as deferred so the arrows wouldn't work. 

 

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
Avatar
Anastasia

Thank you for the update and for pointing this out, Krista! In case anyone else is interested: it is not possible to add any type of dependency to cancelled and deferred tasks. However, if a dependency was set up before the task received one of these statuses, the dependencies will stay in place.

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: getting dependency arrows in timeline view to work