How to show Duration, Allocation and Effort in a Widget for an assignee

I am working on a widget that will show duration information per task/assignee.  The assignees are not using the timer to show how long it takes a task.   However the task automatically provides the duration, allocation and effort information.   How can I use the effort mode in the widget to show these three items.  I provided a screenshot. Thanks

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 comment

Irma Viramontes when you configure this in Wrike, you set duration and daily effort allocation and Wrike calculates the total effort. In WA you will need to reverse the process.

For example you could have a pivot table. Add task names as rows, then as values add duration and effort. They should both default to sum/total. You may want to divide the effort by 60 if you want to show it in hours. This is not totally necessary but it will allow you to check that your next step results in the correct values.
then you need to add another value and in the formula editor create a formula that divides effort by duration

if you need to show by assignee then you need to also divide by count of assignees

Miron Mizrahi Community Team at Wrike Wrike Product Manager Become a Wrike expert with Wrike Discover

Miron Mizrahi Wrike Team member Become a Wrike expert with Wrike Discover

1
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: How to show Duration, Allocation and Effort in a Widget for an assignee
[this list is visible for admins and agents only]

Top
Didn’t find what you were looking for? Write new post