Hello, I would like to ask about some dates automatization. I would like my dates will be set automatically according to the previous task. For example, when I set for Task 1 date "January 1st", I would like the date at Task 2 will be automatically set on "January 2nd". Is that possible?

Thank you all 🙂

0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 comment

Hi Barbora,

you can add dependencies to tasks, this should solve your request.

See Editing Task Dependencies on the Gantt Chart – Wrike Help Center