Dates

Hi,

 

I'm wondering if i have done something wrong or haven't selected something. But i have two current issues around dates on wrike. 

1. When i change the date of a sub task, the higher level task date does not change. So I have to manually change the higher task to reflect the finish dates of the sub tasks. 

2. When i add a dependency, the tasks that are linked to this dependency do not change as well. 

Upvote 0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos
1 comment
Avatar
Stephen

Hi Jared, and thanks for your post.
 
1. You are not doing anything wrong here. Task's dates do not influence the parent tasks dates. There's an existing Product Feedback suggestion on allowing subtasks dates to update parent tasks by Megan which is very popular and this is currently on our Product Team's short-term roadmap. Check out the post and make sure to vote for it and add any additional information by commenting.
 
2. For this, I'll need a little more information or an example of what dependencies and date constraints you've created so I can better understand what you're looking to do. If you're looking to move an entire project of linked dependencies to an earlier or later date I would suggest reading about linking them to a Milestone
 
Looking forward to your reply!
0
👍 Spot On 💡 Innovative Approach 💪 Stellar Advice ✅ Solved 🪄 Remove Kudos

Folllowing List for Post: Dates
[this list is visible for admins and agents only]

Top

Upcoming Live Sessions

Didn’t find what you were looking for? Write new post