KPI

Dear  Sir

Could I get report about each average complete time I've assigned them per week or during date?

0
3 comments
Spot On Innovative Approach Stellar Advice
Avatar

Can you define what you mean by time? Days, hours ?

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

That's by Days. Maybe I could use Excel to calculate it?

0
Comment actions Permalink
Spot On Innovative Approach Stellar Advice
Avatar

Yes, you should run a report if you have the business or enterprise version. You should pull and compare the stat date vs the completed date and perhaps you can use excel to calculate average. But I would suggest using mode vs average because if you have some outliers for duration that skew your results. Compare (mean, median and mode). 

0
Comment actions Permalink