Workload - show allocated hours for each day

5 comments

  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Anastasia

     Hi Martin! All tasks should be shown on the Workload, but there are a few things to check to make sure they're there:

    • Only scheduled tasks show on corresponding days, so double check to see whether they've been scheduled.
    • Tasks without assignees fall under the "unassigned" category at the bottom of the list, therefore they may not be visible right away.

    Happy to dig further if this doesn't help, let me know how it goes. :)

    Anastasia Community Team at Wrike ๐ŸŒŽDiscover... Wrike Discover and become a Wrike expert. Click here to get started

    Is this helpful? 0
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Steve Fassnacht

    I second Martin's post. 
    The times shown at the bottom of the workload view are also rounding down. If a resources' allocated hours are 5.8 it actually displays 5.
    Any way to change this display to show decimals or not round?

    Is this helpful? 0
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Anastasia

    Hi Steve, thanks for posting this here! The Workload View does show whole hours, and the values are calculated using mathematical rounding rules. In your case, however, you should see 6 hours on the Workload View, not 5. I'll be happy to open a Support ticket so you could send over a screenshot showing a task (or tasks) with 5.8 allocated hours that show up as having 5 hours on the Workload View. Let me know if you' like me to go ahead and create a ticket. I also want to thank you for sharing your feedback to show decimals on the Workload View!

    Anastasia Community Team at Wrike ๐ŸŒŽDiscover... Wrike Discover and become a Wrike expert. Click here to get started

    Is this helpful? 1
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Maria Boutzoukas

    Hi Anastasia,

    You mentioned 

    • Only scheduled tasks show on corresponding days, so double check to see whether they've been scheduled.

    Is there a way to be able to view the workload information without scheduling the tasks? We want to see how many hours a user has on their plate without having to have specific dates set

     

    Thanks!

    Is this helpful? 0
    Comment actions Permalink
  • Spot On! ๐Ÿ‘ Innovative Approach ๐Ÿ’ก Stellar Advice ๐Ÿ’ช
    Avatar
    Kate Lafferty

    Any progress on whether we can add decimal points? This is really important as we want to track our time in man days i.e. 0.1 man days is 48 minutes and not 1 hour. Please help. 

    Is this helpful? 0
    Comment actions Permalink

Please sign in to leave a comment.

Folllowing List for Post: Workload - show allocated hours for each day
[this list is visible for admins and agents only]

Community

Welcome ๐Ÿ––

Hi there! ๐Ÿ™‚ Want to become a black belt Wrike Ninja? Here's how to earn a Wrike badge

Welcome ๐Ÿ–– Have you checked out this week's Release Notes yet?

Hey! ๐Ÿ‘‹ Curious about something? Visit How To to search and ask the Community for answers.

Welcome! ๐Ÿ‘‹ Figured out a good tip or trick? Share it in Best Practices.

Want to connect your existing software to Wrike? Learn and ask how in the API section.